Jurgen Banadera
Just like to ask for comments and advice, we used golden homes to build our house. they gave us a “quote” for a fixed price contract to build the house. Everything is quoted aside from the kitchen and floor covers which are PC sums. When they start the earthworks, they charging me extra $1,100 because they said that they needed additional hard fill to level my section. I told them that based on our contract
they gave us a quoted price for the earthworks which means that it is a fixed price. Can the builder charge me extra even though we agreed to the quote they submitted for the earthworks?