Who is ensuring what’s done at each stage is (1 ) in the right place, (2) to a...

Read this thread as context for better builder due diligence. Original historical wording is preserved and comments are not independently verified unless labelled.

Source and review policy

This thread is one source, not a verdict

Historical comments are preserved for context with original wording where possible. They are not independently verified unless labelled, and may not reflect current circumstances. Use them alongside public records, third-party review sources, contract checks, and a direct response from the builder.

Mr Fred

We are building with a big brand company. The foundations not your normal slab as its 200+ m2 and at one end the slab will be 1m off he ground. The foundations also include Poly Rock in part of the higher end. My question is about supervision of the site by the build company. We have a point of contact for this part of the build – a slab manger. Earthworks are done, hard fill in the centre of the foundations and where the foundations built up there’s a trench with a concrete base and all the reinforcing rods up. The block layers have done their bit. So that’s the 3rd tradie company to do wok so far. My point is: all the above has happened without the Slab Manager ever setting foot on the site over 6-8 weeks. Who is ensuring what’s done at each stage is (1 ) in the right place, (2) to a good trade standard? Is this normal build practice? Is it due to a shortage of Supervisors? or should the foundations be being checked by the slab manager at stages during the work so far. Perhaps whats happened is fine? Note: the consulting engineers have been on site and failed the earthworks (soil related, not quality of work related) and remedial works carried out. Is our experience with the Slab Manger typical? Cheers
Reply
Historical discussionNot independently verified
Source detailsComment #117835Source link

Chris C

Hi Fred, By ‘Poly Rock’ I assume you mean blocks of polystyrene under the concrete slab, in place of soil or crushed stone etc. Used quite commonly here, even on major civil contracts. No problem in principle. Regarding whether your ‘Slab Manager’ never appearing on Site is typical I don’t know, but it sounds a bit odd. I assume you must be watching the Site constantly enough to know he/she never slips round for a quick look on the way home. If you’re sure on that, and he/she’s your ‘point of contact’ why not give him/her a call, or call the company. If I were building I’d expect some kind of contact and feedback on progress from the builder, at least every week or two. Before doing that I suggest you check at what stages the work is supposed to be inspected and signed off by Council. From you reference to the engineer looking at, and requiring remedial work, on the earthworks obviously someone is keeping some kind of eye on things. But bear in mind that up now it’s possible that most of the work done (other than the earthworks you mentioned) is not ‘covered’ work, by which I mean it has not been covered by other work, so it can no longer be inspected. Perhaps the Slab Manager and Council will appear just in time to check stuff that’s about to be covered up.
Reply
Historical discussionNot independently verified
Source detailsComment #117836Reply to #117835Thread #117835Source link

Mr Fred

Hi Chris, My reference to Poly Rock is a specialised lightweight fill used instead of hard fill for heights above 600mm fill height. This was specifically required by the engineers and isn’t the white polystyrene blocks used as part of the slab. In terms of the project manager for this stage not being on site, we know this because he has tle me that he’s not been on site. Strangely the day I questioned who was keeping an eye on the various trades and the quality of their work, he phoned my the next morning from the site!!!!
Reply
Historical discussionNot independently verified
Source detailsComment #117853Reply to #117836Thread #117835Source link